Back to Blog

Case Study: 500kWp Cold Storage Solar + 1MWh BESS — Epping Industria

How a Western Cape cold storage facility eliminated load-shedding exposure and cut electricity costs by 38% using a Rent-to-Own structured solar and battery system — with R0 upfront investment.

Project snapshot: 500kWp rooftop solar PV + 1MWh LFP BESS  ·  Epping Industria, Cape Town  ·  Commissioned Q3 2024  ·  RTO structure via SOCO CAPITAL

The Challenge

Our client operates a 12,000m² cold storage and logistics facility in Epping Industria, Cape Town. With ammonia refrigeration running 24/7 and a peak demand of approximately 820kVA, the facility sits on a Megaflex tariff with significant peak-period energy and demand charges.

The business faced two compounding pressures heading into 2024:

The facility already had two 500kVA diesel generators, but running them continuously was financially unsustainable and operationally disruptive. The management team needed a permanent solution that did not require capital deployment from a business already managing tight margins.

The Solution

SOCO ENERGY proposed and designed a hybrid solar + BESS system optimised for the facility's Megaflex tariff structure and load profile:

Solar PV — 500kWp

1,250 × 400Wp monocrystalline bifacial panels installed across the facility's north-facing warehouse roof sections. The system was designed to maximise Standard-period generation (10:00–18:00) when the tariff is highest and the cold storage loads are at their peak. Average modelled annual yield: 780 MWh.

Battery Energy Storage — 1MWh LFP

A 1MWh lithium iron phosphate battery system (4 × 250kWh containerised units) with a 500kW inverter. The dispatch strategy was programmed for three simultaneous functions:

Financing Structure

The full system (solar + BESS + installation + monitoring) was financed via SOCO CAPITAL's Rent-to-Own product over a 60-month term. The monthly RTO payment was set at 65% of the client's average monthly electricity saving — ensuring positive cashflow from month one.

Results (First 6 Months of Operation)

38%
Reduction in grid electricity costs
R248k
Average monthly saving
R0
Upfront capital deployed

Load-shedding resilience

During the Stage 4 and Stage 6 events in May–June 2024, the facility experienced zero product temperature excursions. The BESS provided seamless transition to backup power ahead of generator start — eliminating the 8–12 second gap that previously caused refrigeration control system resets.

Demand charge reduction

Network Demand Charges reduced by an average of R62,000/month — accounting for 25% of the total saving — through consistent BESS dispatch during Peak demand windows.

Diesel savings

Generator runtime reduced by 94% compared to the pre-installation baseline. Diesel spend dropped from an average of R85,000/month to under R5,000/month.

Client Comment

"We went from a situation where load-shedding was an existential risk to our cold chain compliance to one where we barely notice it. The financial case was compelling — but the operational peace of mind was the real win."

— Operations Director, Epping Cold Storage Facility

Ready to act on this?

Talk to the SOCO ENERGY team.

Our engineers and finance team are ready to run the numbers for your site — no obligation, 48-hour turnaround on proposals.

Get a Free Assessment Explore Financing